Data Centre Facility Alpha

All Projects
Previous 01 / 19 Next
CLIENT / OWNER Sinar Primera dan Gaw Capital Partners
LOCATION Nongsa, Batam
YEAR 2024-2025
TOTAL IT LOAD 9MW

Scope Of Work:

  • Electrical System works from MV, Transformer to RMU
  • LV Switchgear & Distribution
  • UPS system with Li-ion battery
  • Cooling System for Datahall & PTU, with Fanwall & CRAC units
  • Containerised Power Train concept
  • Container for Transformer Kiosk and Power Train Units to house LV Switchgear, UPS and battery
  • Unique concept of modular container conjoined on site
  • First of its kind implementation
Data Centre Facility Alpha Overview
Successfully Delivered